Getting your retention back: a subcontractor's guide
Updated October 2026
Retention is a percentage (often 3% to 5%) held back from each payment as security for defects. It's normally released in two halves: the first at practical completion and the second at the end of the defects or rectification period.
Know your triggers
Your subcontract should say what triggers each release. Since 2011, the Construction Act stops payment being made conditional on performance under another contract, so for most construction contracts a clause tying your retention to the main contract's certificate is likely to be ineffective (section 110(1A)). The exact position depends on your contract wording and the date it was made.
Apply for it
Treat retention release like any other payment: send an application on the right date. The payment notice and pay less notice rules then apply to it, so a payer who wants to keep it against defects needs to give a valid pay less notice in time.
Don't let it slip
The second half often falls due a year or more after you've left site, which is why so much retention is never collected. NotifiedSum records both release dates and emails you before each one.
If retention is overdue, LatePay UK can chase it with statutory interest.
Work out your dates in seconds
Free, no sign-up. Scheme or your own contract terms.
Open the calculatorNotifiedSum is a calculation and record-keeping tool, not a law firm, and nothing on this site is legal advice. Your contract's own payment terms usually apply instead of the Scheme, and whether a notice is valid depends on its content and how it was served. Check important deadlines against your contract, and take advice from a construction solicitor or adjudication specialist before relying on them in a dispute.